Response to Mayor Hughson, provided by Senior Engineer, Jacque Thomas:
The graphic reflecting historic flood events are representative of the of what has occurred in the neighborhood. This graphic does not include all flood events, only those that have been determined to above a certain level. The purpose of the graphic is to show the level of flooding on the Blanco River that then spills into the Blanco Gardens neighborhood and how often that has occurred. Additional substantial information is available in the form of modeling reports that are available to public for more detailed information. The May 2015 flood as shown on the graphic does not show an exact frequency, only that it is above the 100-yr event. The graphic overall is provided for a visual talking point, it is not the final data used for the design and assessment of the project.
Response to Mayor Hughson, provided by Senior Engineer, Jacque Thomas:
The Blanco Riverine Flood Mitigation Project, as shown in the presentation, is funded by multiple grants. For CDBG-DR (which has the 7yr timeframe) funding allocated to BR the activity to be completed is acquisition/relocation which is on schedule. BR funding for construction is from CDBG-MIT (which has a much extended timeframe) is also on schedule for expenditure well prior to expiration of MIT grant funds.