Consider an appeal of the administrative decision denying a request to vary from the requirement to install electrical facilities underground rather than overhead in the Whisper Industrial Development.
 

JHughson

CoSM Members
There are some oddities in the packet under this one. A blank application on page 327. The same map in the packet for #16 and #15 (pages 297 and 328).
Page 327 and 330 appear to be the same request. Page 328 and 331 are the same map. Same for 329 and 332.

Is there a compromise option for #16?
 

COSM_Admin

Administrator
Staff member
Responses provided by Shaun Condor, Director of Engineering and Capital Improvement:
Pages 330-332 is the applicant’s appeal letter. Pages 325-329 is Staff’s response letter in which we include a copy of the Appeal Application for their use and a copy of their letter for reference. The map on page 328 differs from page 297 in that they identify the request for this item in red (attached).

Unlike Item #15 this item is only in the Light Industrial portion of the development. A compromise was not proposed as there only appears to be the two options:

1. Deny the appeal and require they go underground

2. Approve to allow the overhead installation.
 