Item 19: Electric Utility Rates for Large Independent, Redundant Service and Large Distributed Generation Standby Service

Status
Not open for further replies.

COSM_Admin

Administrator
Staff member
Consider approval of Ordinance 2022-40, on the first of two readings, increasing electric utility rates charged for Large Independent, Redundant Service and Large Distributed Generation Standby Service customers; and including procedural provisions; and providing an effective date.
 

AGarza

Council Member
I had some issues downloading the meeting material-- so this may have been addressed somewhere in the attachments---
What are some examples or the criteria for Large Independent, Redundant Service and Large Distributed Generation Standby Service ?
 

COSM_Admin

Administrator
Staff member
I had some issues downloading the meeting material-- so this may have been addressed somewhere in the attachments---
What are some examples or the criteria for Large Independent, Redundant Service and Large Distributed Generation Standby Service ?
Response provided by Tyler Hjorth, Director of Utilities:
LIRS
Applies to commercial customers with a maximum metered demand of 1 MW (megawatt) or greater, and the customer requires two or more independent, redundant services.
LDGS
Applies to commercial customers with distributed generation resources that are at least 1 MW (megawatt) but less than 10 MW and that generate a significant portion (or all) of the customer's load requirement.
 