Response provided by Shaun Condor, Director of Engineering & Capital Improvement:
Spreadsheet is attached. It identifies projects that are deferred. Projects are deferred for several responses such as staff capacity and/or timing of other related projects/development. The majority of projects deferred fall into these categories. There is not a list of specific reasons for every single deferred project.
This will be discussed during the presentation, but for the FY 2024 list, the 3 biggest deferred projects are:
- 555 - Highway 80 Utility Project
- Project has been slowed down so we can re-apply for Texas Water Development Board funding in hopes of reducing how much impact fee funding is required to fund construction.
- 795 - Airport - DOL Land Acquisition
- Staff is waiting for an appraisal from the Department of Labor to specify how much the City is going to have to pay for the land.
- An appraisal is expected within the next month or two based off our latest correspondence with the DOL. Once the appraisal is received, we will cancel any unused funds.
- 718 - UPRR Quiet Zone - Uhland Rd. Quad Gates
- The project is receiving $1.324 M in ARPA funding.
- Staff is deferring $1M in General funds until we can confirm the ARPA funding will cover the full project cost. UP is expected to provide a cost this summer and staff will release funding not required to complete the project at that time.