Item 07: San Marcos Shared Use Pathway

Status
Not open for further replies.

COSM_Admin

Administrator
Staff member
Consider approval of Resolution 2023-88R, supporting the City’s application for the San Marcos Shared Use Pathway project to the Texas Department of Transportation’s 2023 Transportation Alternatives Set-aside (TA) call for projects; and declaring an effective date.
 

JHughson

CoSM Members
ARF states "current construction cost is estimated at $1.1M"
Draft FY 2024-2033 shows total of $900,000.
Do we need to update the CIP?
 

COSM_Admin

Administrator
Staff member
Response provided by Shaun Condor, Director of Engineering/CIP
The CIP has $100K for design in FY 2024 and $800K for construction in FY2026. Since the construction funding is not needed until FY2026, we can update it in the future once we get the design finalized and a better cost estimate for this work.
 