Item 13: Utility Fee Reimbursement

Status
Not open for further replies.

COSM_Admin

Administrator
Staff member
Consider approval of Resolution 2021-259R, approving a Change Order to the construction contract with Hunt San Marcos Development, LLC in the amount of
$84,874.10 to reimburse the company for utility fees it paid to Bluebonnet Electric Cooperative, Inc. for electric service for the Public Services Center to avoid disruption of
the construction schedule; authorizing the City Manager or his designee to execute the appropriate documents relating to the Change Order on behalf of the City, and declaring an
effective date.
 