I see this in the background information:
"Based on a development agreement with the City, the La Cima developer is responsible for the design of this new 18” wastewater line."
Why?
Response provided by Rey Garcia, Senior Engineer:
The La Cima developer was responsible for the
original design of the project. During the 90% design phase it was decided to add a storm sewer outfall associated with the Bishop Street Drainage project and to realign the wastewater line so that only one area would be disturbed at one time and minimize the amount of easements required within a lot owned by Hays County Emergency Services Division. This ACIS#5 is for the remaining design/easement effort as well as bidding and construction phase services and broken down as follows:
- Additional Design and Permitting Services, $8,250
- Easement Documents, $1,750
- Bidding Phase Services, $7,735
- Construction Administration, $32,205
Originally easements were going to be dedicated by plat during the Hays ESD development process. The Hays ESD project was then put on hold due to financial challenges requiring easement dedication by separate instrument. The original design contract as well as all ACIS’s 1 through 4 were also associated with the change in wastewater alignment and associated easement documents. Total prior design and easement effort is $40,640 and broken down as follows:
Original Design Contract, $31,340 (Design, Permitting, Meetings)
ACIS #1, $1,300, (Additional topo survey required for redesign)
ACIS #2, $1,750 (Survey Metes and Bounds for Hays ESD Easement)
ACIS #3, $1,750 (Survey Metes and Bounds for Hays County Easement)
ACIS #4, $4,500, (Topo Survey and Metes and Bounds for existing wastewater line abandonment)
Total redesign and easement effort to date including this ACIS#5 is $50,640.