Item 15: Wallace Addition Subdivision Improvements Project

Status
Not open for further replies.

COSM_Admin

Administrator
Staff member
Consider approval of Resolution 2024-219R, approving an On-Call Agreement with Tetra Tech, Inc., for engineering design, bid and construction phase services for the Wallace Addition Subdivision Improvements Project, in an amount not to exceed $2,000,000.00; authorizing the City Manager, or her designee, to execute the agreement on behalf of the city; and declaring an effective date.
 

JHughson

CoSM Members
This sentence is concerning. Please explain.
Project 2: Wallace Addition Subdivision Improvements... The scope does not include the full reconstruction
of streets and sidewalk within the entire neighborhood.

Will they have less after the project than they have now?
 

COSM_Admin

Administrator
Staff member
Response provided by Shaun Condor, Director of Engineering:
The project will replace any sidewalks and streets that are impacted by construction. The project is expected to have some streets with no work or minimal work. The sentence is just clarifying not every single street in the Wallace Addition Subdivision will get new streets and sidewalk as a result of this project. Once construction is completed, the neighborhood will have more sidewalks than when the project started.
 
Status
Not open for further replies.
Top